Civmec was awarded the civil concrete package of over 14,000 cubic metres of concrete works, as well as the design, fabrication, construction and installation of 30 field-erected tanks. In addition to those initial works, we were awarded a bridging scope, which consisted of the installation of pipe rack modules, thickeners and mixer settler vessels.
Following this, we were awarded the major contract for the structural, mechanical, piping, electrical and
instrumentation (SMPE&I) installation works on the project. This package comprises approximately 2,500 tonnes of structural steel, 87 kilometres of piping installation, and 585 kilometres of cable installation with 26,000 terminations.
As Australia’s first fully integrated facility for the production of separated rare earth oxides, the project represents a strategically important development in Australia’s critical minerals processing capability, with our works reinforcing our position as a trusted delivery partner for complex processing facilities.