The packages include greenfields and brownfields scopes with the construction of a new primary crushing facility, Run Of Mine (ROM) pad, overland conveying circuit and modifications to the Coarse Ore Stockpile (COS) and downstream conveying system.
The greenfields construction includes civil works for the primary crusher and transfer stations, installation of the associated structural steel, and several kilometres of low-level modules for the overland conveyor.
Fabrication and modularisation are being undertaken from both our west and east coast facilities.
In a demonstration of the Civmec values of innovation and collaboration, our team cooperated with the client and their engineers to offer an alternative formwork solution and establish a precast yard onsite, thereby somewhat de-risking the shutdown works and increasing schedule efficiency.
Brownfields works are now complete, with greenfields scheduled for completion during the 2025 financial year.